- It was mentioned that in May all the VMTSA were OK as some Xrays were done (by
chance) => See
VB's LMC talk and
other slides from VB. In fact, in VB's talk an X-ray campaign (of the 10th
and 12th of May) is mentioned for LSS2 only as there were no Xrays for LSS8.
- Several bench impedance measurements done during the 2011-2012 shutdown:
-
13/01/2012 => Antenna (in December) and
wire (in January) measurements with the old (long, i.e. from 2011) RF fingers.
-
01/02/2012 => Wire measurements with the
new (shorter, i.e. for 2012) RF fingers.
- 02/02/2012 => Wire
measurements with the old (long, i.e. from 2011) RF fingers and in particular
also with bellow empty (i.e. without RF fingers at all for this bellow, see
slide 2).
-
09/02/2012 => Wire measurements with the new
(shorter, i.e. for 2012) RF fingers.
-
13/02/2012 => Wire measurements with the
new (shorter, i.e. for 2012) RF fingers adding some ferrite blocks.